Pursuant to its competences as defined by law, the State Electricity Regulatory Commission (SERC) has initiated the proceedings for setting of tariffs for operation of the Independent System Operator and tariffs for system and ancillary services, upon the application of the regulated entity. 

The Independent System Operator in Bosnia and Herzegovina Sarajevo, as the regulated company, submitted necessary documentation in which it presented the revenue and expenditure requirements as well as costs it intends to include in tariffs for its services. Pursuant to the Law Establishing an Independent System Operator in BiH, the company is obligated to prove that the proposed tariffs meet requirements of regulatory rules and regulations.

The revenue requirement requested for 2019 amounts to 9,657,336 BAM, the requested tariff for operation of the independent system operator to be paid by customers amounts to 0.070203, while the tariff to be paid by generators amounts to 0.007796 fening/kWh. The proposed tariff for system service amounts to 0.647 fening/kWh.

The tariff application will be resolved pursuant to the criteria as laid down in the Law on Transmission of Electric Power, Regulator and System Operator of Bosnia and Herzegovina and Tariff Pricing Methodology for Services of Electricity Transmission, Operation of ISO and Ancillary Services.

When deciding on the application, SERC will obey to the maximum the basic principles that require that tariffs should be fair and reasonable, non-discriminatory, established on objective criteria, based on justified costs and determined in a transparent manner.


The State Electricity Regulatory Commission informs all interested parties that they will have access to the complete documentation at the SERC premises until 16 November 2018, and may send written comments regarding the subject of the proceedings to the SERC address (Tuzla, Đorđa Mihajlovića 4, fax: 035/302077, e-mail: This e-mail address is being protected from spambots. You need JavaScript enabled to view it ). The tariff application is also available on the SERC web site (HERE).


At the same time the State Electricity Regulatory Commission issues

PUBLIC NOTICE ON FORMAL PUBLIC HEARING

Crucial facts in the tariff proceedings will be determined at a formal public hearing to be held on Tuesday, 11 December 2018 in the Congress Hall of the Tuzla Hotel in Tuzla starting at 11:00 hrs.

The formal hearing is open to the public but the present parties representing the public may not give any comments. The parties who are interested to participate in the formal public hearing procedure in the capacity of interveners have to submit their requests in writing no later than 16 November 2018. Intervener status may be granted to a party who provides evidence of direct interest in the tariff proceedings which differs from the general public interest.